GEPCO New Connection — Application, Documents & Fees 2026

Apply for new GEPCO electricity connection. Documents, costs, timelines for residential, commercial, and industrial in Gujranwala, Sialkot, and Gujrat.

GEPCO New Connection — Application, Documents & Fees 2026

Connection Types

CategoryLoadCommon Use
Residential 1-PhaseUp to 5 kWHomes
Residential 3-Phase5–50 kWLarge homes
Commercial 1-PhaseUp to 5 kWShops
Commercial 3-Phase5–500 kWMarkets
IndustrialVariesFactories
AgriculturalVariesTube-wells

Required Documents

Residential

  • CNIC original + 2 copies
  • Property ownership documents
  • Rent agreement + landlord NOC (tenants)
  • Site plan / location map
  • Load estimate
  • 2 passport photos

Industrial additions

  • SECP registration / NTN
  • Environmental NOC
  • Load study from licensed engineer
  • Factory layout plan

Application Process

  • Visit GEPCO subdivision office
  • Submit application with documents
  • SDO team inspects within 7–14 days
  • Demand notice with charges issued
  • Pay at authorized bank within 15 days
  • Submit paid challan
  • Meter installed and connection activated

Costs

TypeDepositService ChargeMeterTotal
Residential 1-PhaseRs 5,000–8,000Rs 2,000–4,000Rs 3,000–5,000Rs 10,000–17,000
Residential 3-PhaseRs 15,000–25,000Rs 5,000–10,000Rs 8,000–12,000Rs 28,000–47,000
CommercialRs 10,000–50,000Rs 3,000–15,000Rs 4,000–15,000Rs 17,000–80,000
IndustrialRs 50,000+VariesRs 20,000+Rs 100,000+

Timelines

TypeNEPRA StandardTypical
Single Phase14 days15–30 days
Three Phase21 days30–45 days
Commercial30 days30–60 days
Industrial45 days60–120 days

Frequently Asked Questions

How to apply for GEPCO connection?

Visit subdivision with CNIC, property docs, load estimate. Pay demand notice after inspection.

Cost of GEPCO residential connection?

Rs 10,000–17,000 for single-phase including deposit, charges, and meter.

How long does it take?

14 days NEPRA standard, practically 15–30 days.

Can tenants apply?

Yes with landlord NOC and rent agreement.

Is deposit refundable?

Yes, upon permanent disconnection minus dues.

Can I upgrade 1-phase to 3-phase?

Yes. Apply for load enhancement at subdivision.

Industrial connection process?

Needs SECP registration, load study. Takes 60–120 days.

What if GEPCO delays?

File CCMS complaint, escalate to NEPRA.

Need building NOC?

New constructions may need completion certificate.

Can I apply online?

Initial applications are in-person. Some tracking available online.