Connection Types
| Category | Load | Common Use |
|---|---|---|
| Residential 1-Phase | Up to 5 kW | Homes |
| Residential 3-Phase | 5–50 kW | Large homes |
| Commercial 1-Phase | Up to 5 kW | Shops |
| Commercial 3-Phase | 5–500 kW | Markets |
| Industrial | Varies | Factories |
| Agricultural | Varies | Tube-wells |
Required Documents
Residential
- CNIC original + 2 copies
- Property ownership documents
- Rent agreement + landlord NOC (tenants)
- Site plan / location map
- Load estimate
- 2 passport photos
Industrial additions
- SECP registration / NTN
- Environmental NOC
- Load study from licensed engineer
- Factory layout plan
Application Process
- Visit GEPCO subdivision office
- Submit application with documents
- SDO team inspects within 7–14 days
- Demand notice with charges issued
- Pay at authorized bank within 15 days
- Submit paid challan
- Meter installed and connection activated
Costs
| Type | Deposit | Service Charge | Meter | Total |
|---|---|---|---|---|
| Residential 1-Phase | Rs 5,000–8,000 | Rs 2,000–4,000 | Rs 3,000–5,000 | Rs 10,000–17,000 |
| Residential 3-Phase | Rs 15,000–25,000 | Rs 5,000–10,000 | Rs 8,000–12,000 | Rs 28,000–47,000 |
| Commercial | Rs 10,000–50,000 | Rs 3,000–15,000 | Rs 4,000–15,000 | Rs 17,000–80,000 |
| Industrial | Rs 50,000+ | Varies | Rs 20,000+ | Rs 100,000+ |
Timelines
| Type | NEPRA Standard | Typical |
|---|---|---|
| Single Phase | 14 days | 15–30 days |
| Three Phase | 21 days | 30–45 days |
| Commercial | 30 days | 30–60 days |
| Industrial | 45 days | 60–120 days |
Frequently Asked Questions
How to apply for GEPCO connection?
Visit subdivision with CNIC, property docs, load estimate. Pay demand notice after inspection.
Cost of GEPCO residential connection?
Rs 10,000–17,000 for single-phase including deposit, charges, and meter.
How long does it take?
14 days NEPRA standard, practically 15–30 days.
Can tenants apply?
Yes with landlord NOC and rent agreement.
Is deposit refundable?
Yes, upon permanent disconnection minus dues.
Can I upgrade 1-phase to 3-phase?
Yes. Apply for load enhancement at subdivision.
Industrial connection process?
Needs SECP registration, load study. Takes 60–120 days.
What if GEPCO delays?
File CCMS complaint, escalate to NEPRA.
Need building NOC?
New constructions may need completion certificate.
Can I apply online?
Initial applications are in-person. Some tracking available online.