FESCO New Connection — Application Process & Fees 2026

Apply for a new FESCO electricity connection in Faisalabad region. Documents, fees, timelines, and tips for residential, commercial, and industrial connections.

FESCO New Connection — Application Process & Fees 2026

FESCO Connection Types

CategoryCodeLoadCommon Use
Residential 1-PhaseA-1(a)Up to 5 kWHomes
Residential 3-PhaseA-1(b)5–50 kWLarge homes
Commercial 1-PhaseA-2(a)Up to 5 kWShops
Commercial 3-PhaseA-2(b)5–500 kWMarkets, plazas
IndustrialBVariesFactories, workshops
AgriculturalCVariesTube-wells

Required Documents

For residential connections

  • CNIC original and 2 photocopies
  • Property ownership documents (registry or allotment letter)
  • Rent agreement + landlord NOC (for tenants)
  • Site plan / location map
  • Load estimate with appliance list
  • 2 passport-size photographs
  • Building completion certificate (for new builds)

Additional for industrial

  • SECP registration / NTN certificate
  • Environmental NOC (if applicable)
  • Power load study from licensed engineer
  • Factory layout plan with equipment placement

Application Process

  • Visit your jurisdictional FESCO subdivision office
  • Submit application form with all documents
  • FESCO SDO team inspects premises within 7–14 days
  • Demand notice issued with connection charges
  • Pay demand notice at authorized bank within 15 days
  • Submit paid challan to subdivision office
  • FESCO installs meter and connects premises
  • Connection activated — first bill in next billing cycle

Connection Costs

TypeSecurity DepositService ChargeMeterTotal
Residential 1-PhaseRs 5,000–8,000Rs 2,000–4,000Rs 3,000–5,000Rs 10,000–17,000
Residential 3-PhaseRs 15,000–25,000Rs 5,000–10,000Rs 8,000–12,000Rs 28,000–47,000
CommercialRs 10,000–50,000Rs 3,000–15,000Rs 4,000–15,000Rs 17,000–80,000
IndustrialRs 50,000+VariesRs 20,000+Rs 100,000+

Timelines

TypeNEPRA StandardTypical
Single Phase14 days15–30 days
Three Phase21 days30–45 days
Commercial30 days30–60 days
Industrial45 days60–120 days

Tips for Faster Approval

  • Complete all documents before applying
  • Apply during off-peak months (Oct–Feb)
  • Get internal wiring ready before connection date
  • Follow up weekly at subdivision office
  • File CCMS complaint if timeline exceeds NEPRA standard
  • Check transformer capacity in your area beforehand

Frequently Asked Questions

How to apply for new FESCO connection?

Visit your local FESCO subdivision with CNIC, property docs, and load estimate. Submit application, pay demand notice after inspection, and wait for installation.

Cost of new FESCO residential connection?

Rs 10,000–17,000 for single-phase (5 kW) including deposit, service charges, and meter.

How long does FESCO connection take?

14 days NEPRA standard for single-phase. Practically 15–30 days depending on infrastructure.

Can tenants apply for FESCO connection?

Yes, with landlord NOC and rent agreement plus your CNIC.

Is security deposit refundable?

Yes, upon permanent disconnection minus any outstanding dues.

Can I upgrade from 1-phase to 3-phase?

Yes, apply for load enhancement at your subdivision. Additional deposit and infrastructure costs may apply.

What about industrial connections in Faisalabad?

Industrial connections require load study, SECP registration, and may take 60–120 days. FESCO's M-3 Industrial Estate has dedicated infrastructure.

What if FESCO delays my connection?

File a CCMS complaint, then escalate to NEPRA with your application receipt if unresolved.

Do I need NOC from building authority?

For new constructions, a building completion certificate may be required. Contact your subdivision for specific requirements.

Can I apply online?

Currently, initial applications are in-person at subdivision offices. Some tracking may be available online after submission.

← Back to all articles